RE: To be Rescheduled -Bldg. 56 & 16- Continuation of Fire Alarm
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 25 09:32:15 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mare@mit.edu'" <mare@MIT.EDU>, "'mparker@mit.edu'" <mparker@MIT.EDU>,
"'mbj@mit.edu'" <mbj@MIT.EDU>, "'sorrento@mit.edu'" <sorrento@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'loudib@mit.edu'"
<loudib@MIT.EDU>,
"'claudia@mit.edu'" <claudia@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'pguyer@mit.edu'" <pguyer@MIT.EDU>, "'rha@mit.edu'" <rha@MIT.EDU>,
"'bmalone@mit.edu'" <bmalone@MIT.EDU>,
"'carolr@mit.edu'" <carolr@MIT.EDU>, "'edc@mit.edu'" <edc@MIT.EDU>,
"'kej@mit.edu'" <kej@MIT.EDU>, "'childs@mit.edu'" <childs@MIT.EDU>,
"'wogan@mit.edu'" <wogan@MIT.EDU>,
"'bdfollst@mit.edu'"
<bdfollst@MIT.EDU>,
"'puffer@mit.edu'" <puffer@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 25 Nov 1998 09:30:56 -0500
Update---
Dear Everyone:
I am once again sending out information concerning a new day (Sunday,
Dec. 6) because of conflicts with the Dec. 5 date.
Would you please let me know if this new date and time would or would
not be acceptable to you.
Thank you very much for your patience in this matter.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: 56 & 16
> > Date: 12/6/98
> > Day: Sunday
> > Time: 7 AM - 3 PM
> > System: Fire Alarm Audible testing
> > Duration: 8 hours
> > Reason:
> > Testing on Saturday, 11/21 was not complete. Simplex and
> Cambridge
> * > Fire Department would like to continue this work until
> it is complete
>
> > Effect: Loss of fire alarm system and smoke detectors.
> Audible testing would take place. Again this would be short bursts of
> sound and announcements would be made prior to each testing.
>
>
>