[45929] in Hotline Meeting
RE: Bldgs. W31 and W32 Electric Power and Lighting Shutdown Reque
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 23 07:01:14 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'djmartin@mit.edu'" <djmartin@MIT.EDU>,
"'kenstone@mit.edu'"
<kenstone@MIT.EDU>,
"'regillya@mit.edu'" <regillya@MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Mon, 23 Nov 1998 07:00:08 -0500
Update --
Dear Everyone:
It has been requested that this shutdown begin at 5:00 AM - 6:30 PM
rather than 5:30 AM. We are changing it accordingly.
For your information.
Andrea Nichols
>
> The following Electric Power and Lighting shutdown request for Bldgs.
> W31 and W32 on 12/1 is for your review and comment. Would you please
> let me know whether or not this meets with your approval.
>
> Thanks very much.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: W31 and W32
> > Date: 12/1/98
> > Day: Tuesday
> > Time: 5:00 AM - 6:30 AM
> > System: All Electric Power and Lighting
> > Duration: 1 1/2 hours
> > Reason:
> > To install new main breaker and perform metering upgrades.
> >
> > Effect:
> > Loss of Power: access controls, building power, elevators,
> computers,
> > telephones and lighting; Water: hot domestic water pumps (water
> for
> > kitchen and bathroom faucets), heating hot water pumps (heating for
> > bldg.); Air: supply ventilation, supply cooling, supply heating,
> > exhaust-laboratory, exhaust-general, exhaust toilet and compressed
> > control air.
> >
> >
>