Re: Bldgs. W31 and W32 Electric Power and Lighting Shutdown

daemon@ATHENA.MIT.EDU (Daniel J. Martin)
Fri Nov 20 15:07:32 1998

Date: Fri, 20 Nov 1998 15:09:56 -0500
To: Andrea Nichols <andrea@PLANT.MIT.EDU>,
        "'kenstone@mit.edu'" <kenstone@MIT.EDU>,
        "'regillya@mit.edu'" <regillya@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>
From: "Daniel J. Martin" <djmartin@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
In-Reply-To: <ECFE33C8A3D4D111917900805FBE00003E558D@PLANT.MIT.EDU>

Hi Andrea,

It would be better for Athletics if the time went from 5am-6:30am. 

We already have patrons and staff in our buildings by 6:50am.
PS. This will effect the operation of Building Services cleaning of
Athletic Facilities their shift is Sun.-Th. 11am-7am. 

Go Tech!!

 At 12:06 PM 11/20/98 -0500, Andrea Nichols wrote:
>> To: 	djmartin@mit.edu; kenstone@mit.edu; regillya@mit.edu;
>> dcarlson@mit.edu; cappucci@mit.edu; jfreeman@mit.edu; mwf@mit.edu;
>> shutdowns@mit.edu; opsnote@mit.edu
>> Cc: 	shutdown@plant.mit.edu
>> Subject: 	Bldgs. W31 and W32 Electric Power and Lighting Shutdown
>> Request for 12/1
>> 
>> 
>The following Electric Power and Lighting shutdown request for Bldgs.
>W31 and W32 on 12/1 is for your review and comment.  Would you please
>let me know whether or not this meets with your approval.
>
>Thanks very much.
>
>Andrea Nichols
>Operations Center
>8-7872
>
>> Status: Normal
>> Building: W31 and W32
>> Date: 12/1/98
>> Day: Tuesday
>> Time: 5:30 AM - 7:00 AM
>> System: All Electric Power and Lighting
>> Duration: 1 1/2 hours
>> Reason: 
>> To install new main breaker and perform metering upgrades.
>> 
>> Effect: 
>> Loss of Power:  access controls, building power, elevators, computers,
>> telephones and lighting;  Water:  hot domestic water pumps (water for
>> kitchen and bathroom faucets), heating hot water pumps (heating for
>> bldg.); Air:  supply ventilation, supply cooling, supply heating,
>> exhaust-laboratory, exhaust-general, exhaust toilet and compressed
>> control air. 
>> 
>> 
>