[45873] in Hotline Meeting
FW: Bldg. NW21 - 114, 115, 116, 117, 118, 119, 120, 103, 115, 155
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Nov 18 10:38:16 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Wed, 18 Nov 1998 10:36:57 -0500
FYI and comment if you wish.
Thanks.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Tuesday, November 17, 1998 10:48 AM
> To: 'fulton@psfc.mit.edu'
> Cc: Shutdown; Howard Harrison; David Ferrante; John Denucce; Tom
> Connolly
> >
> The following shutdown request for Bldg. NW21 (see above room listing)
> on 11/20 is for your review and comment. Would you please let me know
> whether or not this meets with your approval.
>
> Thanks very much Matt.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: NW21-114, 115, 116, 117, 118, 119, 120, 103, 115, 155,
> > loading dock & 203 through 216
> > Date: 11/20/98
> > Day: Friday
> > Time: 5:00 PM - 7:00 PM
> > System: Power; Exhaust Fans 1 and 5, Boiler, Condensate Pumps, FCS
> > panel, cooling tower, Exhaust Fan 2, process water, IF-1, P-11.
> > Duration: 2 hours
> > Reason:
> > To install new circuit breaker for rooftop air conditioning unit.
> >
> > Effect:
> > Loss of power: Bldg. power, computers, telephones, lighting,
> > corridors/stairs; water: hot domestic (for kitchen and bathroom
> > faucets), cold lab process (for labs); Air: supply ventilation,
> > exhaust general and exhaust toilet air; Other: Fire Alarm and
> > burglar alarm.
>
>