[45849] in Hotline Meeting
FW: Bldgs. E17 and E18 Shutdown Request for 11/20
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 17 11:02:46 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Tue, 17 Nov 1998 11:01:35 -0500
FYI.
Andrea
> ----------
> From: Andrea Nichols
> Sent: Tuesday, November 17, 1998 10:57 AM
> To: Plant-All; 'wardd@mit.edu'; 'jmganno@mit.edu';
> 'shyoung@mit.edu'; 'aufiero@mit.edu'; 'rmelo@mit.edu';
> 'jmedeiro@mit.edu'
> Cc: Shutdown; 'amba@mit.edu'
> Subject: RE: Bldgs. E17 and E18 Shutdown Request for 11/20
> Importance: High
>
> Update --
> It has been requested that this shutdown be finished by 6:30 AM. We
> will therefore change the start time to 5 AM - 6:30 AM.
> FYI.
> Andrea Nichols
>
> The following shutdown request for Bldgs. E17 and E18 on 11/20 is for
> your information and comment. Would you please let me know whether or
> not this has your approval.
>
> Thanks very much.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: E17 and E18
> > Date: 11/20/98
> > Day: Friday
> > Time: 5:00 AM - 6:30 AM
> > System: Electrical - 480 V Switchgear
> > Duration: 1 1/2 hours
> > Reason:
> > Disconnect wires on existing bus duct to be removed in substation.
> >
> > Effect:
> > Power: Loss of Freight Elevator in E17 and E18 ; Water: loss of
> > chilled water (air conditioning) in E17 and E18 Animal Quarters,
> > E17-347B, 350, 350A and 360; loss of heating hot water in E17 and
> E18;
> > Air: supply ventilation, supply cooling, supply heating,
> > exhaust-laboratory, exhaust-general, exhaust-toilet, compressed
> > control, compressed lab and lab vacuum air. Note; There will be an
> > emergency generator operating to handle the critical equipment in
> the
> > Animal Quarters in E17 and E18.
> >
> >
>
>