FW: Rescheduled - Bldgs. 56 and 16 Fire Alarm Shutdown Request no

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 16 09:40:36 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'kej@mit.edu'" <kej@MIT.EDU>, "'puffer@mit.edu'"
	 <puffer@MIT.EDU>,
        "'bdfollst@mit.edu'" <bdfollst@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'shyoung@mit.edu'"
	 <shyoung@MIT.EDU>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'"
	 <mbj@MIT.EDU>,
        "'mparker@mit.edu'" <mparker@MIT.EDU>,
        "'wogan@mit.edu'"
	 <wogan@MIT.EDU>, "'edc@mit.edu'" <edc@MIT.EDU>,
        "'naylor@mit.edu'"
	 <naylor@MIT.EDU>,
        "'loudib@mit.edu'" <loudib@MIT.EDU>,
        "'claudia@mit.edu'" <claudia@MIT.EDU>,
        "'pguyer@mit.edu'"
	 <pguyer@MIT.EDU>, "'rha@mit.edu'" <rha@MIT.EDU>,
        "'bmalone@mit.edu'"
	 <bmalone@MIT.EDU>,
        "'childs@mit.edu'" <childs@MIT.EDU>,
        "'sorrento@mit.edu'" <sorrento@MIT.EDU>,
        "'rbal@mit.edu'" <rbal@MIT.EDU>
Date: Mon, 16 Nov 1998 09:37:25 -0500

Dear Everyone:
The above rescheduled fire alarm shutdown request now for 11/21 is for
your information and comment.  Would you please let me know whether this
does or does not have your approval.

Thank you very much.

Andrea Nichols
> >Operations Center
> >8-7872
> >
> >> Status: Routine
> >> Building: 56 and 16
> >> Date: 11/21/98
> >> Day: Saturday
> >> Time: 7 AM - 5 PM
> >> System: Fire Alarm
> >> Duration: 10 hours
> >> Reason:
> >> To install new message chip and  perform audible tests for proper
> operation.
> >> Effect:
> >> Testing will not be continuous - will be five minutes at a time.
> The
> >> Safety Office will be advised of this - that office will notify the
> >> Fire Department.
> 
> 
> 
> 