RE: Update - Bldg. E19 - 6th and 7th Floor Shutdown Request now f

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 13 15:21:12 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dturn@mit.edu'" <dturn@MIT.EDU>, "'cashaw@mit.edu'" <cashaw@MIT.EDU>,
        "'lambert@mitvma.mit.edu'" <lambert@mitvma.mit.edu>,
        "'opsnote@mit.edu'"
	 <opsnote@MIT.EDU>,
        "'sico@mit.edu'" <sico@MIT.EDU>,
        "'wbarrett@mit.edu'"
	 <wbarrett@MIT.EDU>,
        "'edie@mit.edu'" <edie@MIT.EDU>,
        "'honiker@mit.edu'"
	 <honiker@MIT.EDU>,
        "'kelley@mit.edu'" <kelley@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Fri, 13 Nov 1998 15:19:08 -0500

Dear Everyone:
The rescheduled shutdown requested date for Bldg. E19 - 6th and 7th
Floors is now for Saturday, November 21. Would you please let me know if
this new date and time (see below) would be all right with you or not.

Thank you again.

Andrea Nichols
> 	Operations Center
> 	8-7872
> 
> 	> Status: Normal
> 	> Building: E19 - 6th and 7th floors
> 	> Date: 11/21/98
> 	> Day: Saturday
> 	> Time: 7 AM - 12 Noon
> 	> System: Supply ventilation, supply cooling and supply heating
> 	> Duration: 5 hours
> 	> Reason: 
> 	> To fabricate/modify belt guard for Air Handler 7 - Supply Fan
> 2
> 	> (PM#700698)
> 	> Effect: 
> 	> Loss of supply ventilation, supply cooling and supply heating
> during
> 	> shutdown period.
> 
> 
> 