[45764] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Bldgs. 56 and 16 Fire Alarm Shutdown Request for 11/10

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 9 12:44:49 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'kej@mit.edu'" <kej@MIT.EDU>, "'puffer@mit.edu'"
	 <puffer@MIT.EDU>,
        "'bdfollst@mit.edu'" <bdfollst@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'shyoung@mit.edu'"
	 <shyoung@MIT.EDU>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'"
	 <mbj@MIT.EDU>,
        "'mparker@mit.edu'" <mparker@MIT.EDU>,
        "'wogan@mit.edu'"
	 <wogan@MIT.EDU>, "'edc@mit.edu'" <edc@MIT.EDU>,
        "'naylor@mit.edu'"
	 <naylor@MIT.EDU>,
        "'loudib@mit.edu'" <loudib@MIT.EDU>,
        "'claudia@mit.edu'" <claudia@MIT.EDU>,
        "'pguyer@mit.edu'"
	 <pguyer@MIT.EDU>, "'rha@mit.edu'" <rha@MIT.EDU>,
        "'bmalone@mit.edu'"
	 <bmalone@MIT.EDU>,
        "'childs@mit.edu'" <childs@MIT.EDU>,
        "'sorrento@mit.edu'" <sorrento@MIT.EDU>,
        "'rbal@mit.edu'" <rbal@MIT.EDU>, Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, "'relices@mit.edu'"
	 <relices@MIT.EDU>,
        "'balkwill@mit.edu'" <balkwill@MIT.EDU>,
        "'mwhelan@mit.edu'" <mwhelan@MIT.EDU>
Date: Mon, 9 Nov 1998 12:36:13 -0500

Update --
	Several of you have asked if it would be all right to stay in
buildings 
	16 and 56 during the Audible Fire Alarm testing- I checked with
the 
	person who will be performing this work (Jack DeNucce) who
advised
	that it will be noisy. Anyone can stay but  may find it very
noisy.
	The audible testing will be going on for 5 minutes each but it
is not
	known at this time how many five minute tests will take place
from 6 
	PM to 12 midnight.

	FYI.

	Andrea Nichols

> The following fire alarm shutdown request for Bldgs. 56 and 16 on
> 11/10
> is for your review and comment.  Would you please let me know whether
> this does or does not have your approval.
> 
> Thank you.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Critical
> > Building: 56 and 16
> > Date: 11/10/98
> > Day: Tuesday
> > Time: 6 PM - 12 midnight
> > System: Fire Alarm
> > Duration: 6 hours
> > Reason: 
> > Testing audibles and visuals to insure life safety.
> > 
> > Effect: 
> > Testing will not be continuous - will be five minutes at a time.
> The
> > Safety Office will be advised of this - that office will notify the
> > Fire Department.
> > 
> > 
> 