Bldg. W16 All Normal Electric Power and Lighting Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 2 14:13:53 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
        "'diegom@mit.edu'" <diegom@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 2 Nov 1998 14:05:26 -0500

> To: 	mwf@mit.edu; mdimauro@mit.edu; diegom@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. W16 All Normal Electric Power and Lighting
> Shutdown Request for 11/10
> 
> 
The following shutdown request for Bldg. W16 (All Normal Electric Power
and Lighting) on 11/10 is for your review and comment. Would you please
let me know whether or not this has your approval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: W16
> Date: 11/10/98
> Day: Thursday
> Time: 6 AM - 7 AM
> System: All Normal Electric Power and Lighting
> Duration: 1 hour
> Reason: 
> To test new emergency power installation.
> 
> Effect: 
> Loss of Power:  Access controls, building power, elevators, computers,
> lighting; Air:  supply ventilation, supply cooling, supply heating,
> exhaust-general air, exhaust toilet air and compressed control air.
> 
> 