Bldg. W16 All Normal Electric Power and Lighting Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 2 14:13:53 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwf@mit.edu'" <mwf@MIT.EDU>, "'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
"'diegom@mit.edu'" <diegom@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 2 Nov 1998 14:05:26 -0500
> To: mwf@mit.edu; mdimauro@mit.edu; diegom@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. W16 All Normal Electric Power and Lighting
> Shutdown Request for 11/10
>
>
The following shutdown request for Bldg. W16 (All Normal Electric Power
and Lighting) on 11/10 is for your review and comment. Would you please
let me know whether or not this has your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: W16
> Date: 11/10/98
> Day: Thursday
> Time: 6 AM - 7 AM
> System: All Normal Electric Power and Lighting
> Duration: 1 hour
> Reason:
> To test new emergency power installation.
>
> Effect:
> Loss of Power: Access controls, building power, elevators, computers,
> lighting; Air: supply ventilation, supply cooling, supply heating,
> exhaust-general air, exhaust toilet air and compressed control air.
>
>