FW: Approved - Bldg. 4 - 201 to 212 Shutdown Request for 10/30
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Oct 27 11:47:28 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
"'graposa@mit.edu'" <graposa@MIT.EDU>,
Gerry Desmond
<gdesmond@PLANT.MIT.EDU>,
Warren Scott <WScott@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
RM-Support
<RM-Support@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>
Date: Tue, 27 Oct 1998 11:39:09 -0500
The following approved chilled water shutdown for Bldg. 4 - 201 - 212 on
10/30 is for your information.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 4 - 201 to 212
> > Date: 10/30/98
> > Day: Friday
> > Time: 7:00 AM - 11:00 AM
> > System: chilled water
> > Duration: 4 hours
> > Reason:
> > To relocate existing valves out of telephone closet.
> >
> > Effect:
> > Loss of chilled water (air conditioning) during 4-hour shutdown
> > period.
>
>