[45567] in Hotline Meeting
RE: Bldg. 24 - 411, 415 and 421 (as well as entire building) Shut
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 26 14:27:15 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
"'devries@mit.edu'"
<devries@MIT.EDU>,
"'hrsweet@mit.edu'" <hrsweet@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'rrhonda@mit.edu'"
<rrhonda@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, "'relices@mit.edu'"
<relices@MIT.EDU>
Date: Mon, 26 Oct 1998 14:18:51 -0500
Correction - this shutdown would be for tomorrow and Wednesday.
Andrea
> ----------
> From: Andrea Nichols
> Sent: Monday, October 26, 1998 12:52 PM
> To: 'schedule@mit.edu'; 'shutdowns@mit.edu'; 'adams@mitlns.mit.edu';
> 'rroscoe@mit.edu'; 'devries@mit.edu'; 'hrsweet@mit.edu';
> 'opsnote@mit.edu'; 'rrhonda@mit.edu'
> Cc: Shutdown; 'relices@mit.edu'
> Subject: RE: Bldg. 24 - 411, 415 and 421 (as well as entire
> building) Shutdown Request for 10/27 and 10/28
> Importance: High
>
> The following shutdown request for Bldg. 24 - 411, 415, 421 (as well
> as the entire building) on 10/27 is for your information and comment.
> Would you please let me know whether this has your approval or does
> not.
>
> Thank you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 24-411, 415 and 421 (also entire building)
> > Date: 10/27-28/98
> > Day: Tuesday and Wednesday
> > Time: 7:30 AM - 2:30 PM each day
> > System: Steam
> > Duration: 2 days
> > Reason:
> > Tie in new units
> >
> > Effect:
> > Loss of low pressure steam. This means there will be no heat
> during
> > this 2-day shutdown.
>
>
>