Bldg. 48 - Electrical Power and Lighting Rescheduled Shutdown for

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 23 09:04:28 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sfrankel@mit.edu'" <sfrankel@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 23 Oct 1998 08:56:23 -0400

> To: 	sfrankel@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 48 - Electrical Power and Lighting Rescheduled
> Shutdown for 10/29
> 
> 
The following rescheduled shutdown for Bldg. 48 electrical Power and
Lighting on 10/29 is for your information and comment. Would you please
let me know if this has your approval or does not.

Sheila  et al- this date and times are negotiable.

Thank you again for your patience.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 48
> Date: 10/29/98
> Day: Thursday
> Time: 5:00 PM - 12 midnight
> System: Electrical Power and Lighting
> Duration: 2 brief outages during shutdown period
> Reason: 
> To perform testing on new automatic transfer switch.
> 
> Effect: 
> Loss of Power: access controls, bldg. power, elevators, computers and
> lighting.
> Outages consist of one brief outage at 5:00 PM and another brief
> outage at midnight.
> 
> 