[45435] in Hotline Meeting
RE: Rescheduled Again - Bldg. 2 Electrical Shutdown Request now f
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 19 08:50:38 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'duggins@math.mit.edu'"
<duggins@math.mit.edu>,
"'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'capozzi@math.mit.edu'"
<capozzi@math.mit.edu>,
"'daisymae@math.mit.edu'"
<daisymae@math.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
Neil Tomlinson
<NTomlins@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>
Date: Mon, 19 Oct 1998 08:42:33 -0400
Dear All:
It has been requested that this shutdown request be rescheduled from
10/22-23 to 11/5 PM - 11/6 AM. Would you please be good enough to let me
know if these new dates would be suitable for your schedules.
Thanks very much --again.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Routine
> > Building: 2
> > Date: 11/5/6
> > Day: Thursday PM - Friday AM
> > Time: 10 PM (11/5) - 8 AM (11/6)
> > System: All Power & Lighting: Electrical - main switch gear in
> Rm. 017
> > Duration: 10 hours
> > Reason:
> > Relocate Panel in transformer room
> >
> > Effect:
> > Loss of Power: Access controls, bldg. power, computers,
> lighting;
> > Water: Chilled water (air conditioning); Air: Supply
> ventilation,
> > supply cooling, supply heating, exhaust laboratory air;
> exhaust
> > general air and exhaust toilet air;
>
>
>