Bldgs. E17 and E18 (Animal Facility) Shutdown Request for 10/20
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 15 08:59:56 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wardd@mit.edu'" <wardd@MIT.EDU>, "'jmganno@mit.edu'"
<jmganno@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
Neil Tomlinson
<NTomlins@PLANT.MIT.EDU>,
"'wlynch@mit.edu'" <wlynch@MIT.EDU>,
"'wgreene@mit.edu'" <wgreene@MIT.EDU>,
"'igergin@mit.edu'"
<igergin@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Thu, 15 Oct 1998 08:51:40 -0400
> To: wardd@mit.edu; jmganno@mit.edu; shyoung@mit.edu
> Cc: shutdown@plant.mit.edu; Neil Tomlinson; wlynch@mit.edu;
> wgreene@mit.edu; igergin@mit.edu; shutdowns@mit.edu
> Subject: Bldgs. E17 and E18 (Animal Facility) Shutdown Request
> for 10/20
>
>
The following shutdown request for Bldgs. E17 and E18 (Animal Facility)
on 10/20 is for your review and comment. Would you please let me know
whether this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E17and E18
> Date: 10/20/98
> Day: Tuesday
> Time: 7:00 AM - 1:00 PM
> System: Emergency Power
> Duration: 6 hours
> Reason:
> Required to move gas supply to the Emergency Generator to allow for
> steel erection.
>
> Effect:
> Loss of Emergency Generator and Emergency power during this 6-hour
> shutdown.
>
>