Bldg. NW16 - All (Electric Power & Lighting Shutdown) on 10/16
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 15 08:33:54 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'fulton@psfc.mit.edu'" <fulton@psfc.mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: RM-2ndShift <rm-2ndshift@MIT.EDU>, RM-3rdShift <rm-3rdshift@MIT.EDU>,
"'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
D-Zone
<D-Zone@MIT.EDU>
Date: Thu, 15 Oct 1998 08:26:02 -0400
> To: fulton@psfc.mit.edu; shutdowns@mit.edu
> Cc: RM-2ndShift; RM-3rdShift; shutdown@plant.mit.edu; D-Zone
> Subject: Bldg. NW16 - All (Electric Power & Lighting Shutdown)
> on 10/16
>
>
The following shutdown for Bldg. NW16 - All (Electric Power & Lighting)
on 10/16 is for your review and comment. This again is at the behest of
Com Electric.
Would you please let me know if this has your approval by 2:00 PM today.
Thanks Matt.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: W16
> Date: 10/16/98
> Day: Friday
> Time: 3 AM - 8 AM
> System: Electric Power & Lighting
> Duration: 5 hours
> Reason:
> For Com Electric to replace faulty 5 KV equipment on Pole
>
> Effect:
> Loss of Power: access controls, building poer, elevators, computers,
> telephones, lighting; Air: supply ventilation, supply cooling,
> supply heating, exhaust-laboratory, exhaust general exhaust toilet,
> compressed conrtrol and compressed lab air.
>
>