FW: Approved - Bldg. W91 Cooling Towers Shutdown Request for 10/1

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Oct 9 13:06:23 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'"
	 <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
        Tom Delena <tdelena@PLANT.MIT.EDU>,
        Warren Scott <WScott@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        RM-Support
	 <RM-Support@MIT.EDU>
Date: Fri, 9 Oct 1998 12:58:33 -0400

The following approved shutdown for Bldg. W91 cooling Towers on 10/16 is
for your information.

Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Routine
> > Building: W91
> > Date: 10/16/98
> > Day: Friday
> > Time: 7:30 AM - 300 PM or until completion
> > System: Cooling Towers for chillers
> > Duration: 8 hours or more
> > Reason: 
> > Clean Towers- change belts, grease bearings, clean nozzles.
> > 
> > Effect: 
> > Will take one cooling tower down at a time - no effect on chiller
> > operation.
> > 
> > 
> 