Re: W8 (Pierce Boathouse) High Voltage Electrical system

daemon@ATHENA.MIT.EDU (Daniel J. Martin)
Fri Oct 2 11:47:30 1998

Date: Fri, 02 Oct 1998 11:48:57 -0400
To: Andrea Nichols <andrea@PLANT.MIT.EDU>,
        "'stucrew@mit.edu'" <stucrew@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
From: "Daniel J. Martin" <djmartin@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
In-Reply-To: <ECFE33C8A3D4D111917900805FBE0000335421@PLANT.MIT.EDU>

Andrea,
I will defer to Stu, whether this works for his program on the perscribed
dates!

Go Tech!!

At 02:01 PM 10/1/98 -0400, Andrea Nichols wrote:
>> To: 	stucrew@mit.edu; djmartin@mit.edu; shutdowns@mit.edu
>> Cc: 	shutdown@plant.mit.edu
>> Subject: 	W8 (Pierce Boathouse) High Voltage Electrical system
>> Shutdown Request for 10/7 PM - 10/8 AM
>> 
>> 
>The following High Voltage Electrical system Shutdown Request for Bldg.
>W8 (Pierce Boathouse) on 10/7 PM - 10/8 AM is for your review and
>comment. Would you please let me know whether this does or does not have
>your approval.
>
>Thank you.
>
>Andrea Nichols
>Operations Center
>8-7872
>
>> Status: Normal
>> Building: W8 (Pierce Boathouse)
>> Date: 10/7/08
>> Day: Thursday
>> Time: 7 PM (10/7) - 1 AM (10/8)
>> System: High Voltage Electrical (all power & lighting)
>> Duration: 6 hours
>> Reason: 
>> Move line to install handicap elevator and ramp.
>> 
>> Effect: 
>> Loss of Power:  access controls, building power, computers, lighting,
>> corridors/stairs;  Water:  Heating hot water;  Air:  Supply
>> ventilation, supply heating, exhaust general air, exhaust toilet air,
>> compressed control air;  Other:  Boiler:
>> 
>> 
>