[44974] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 2 and possibly 4-371 and 382 Rescheduled Shutdown Request f

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 17 16:18:27 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
        "'duggins@math.mit.edu'" <duggins@math.mit.edu>,
        "'juliec@mit.edu'"
	 <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
        "'daisymae@math.mit.edu'" <daisymae@math.mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'seyferth@mit.edu'" <seyferth@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 17 Sep 1998 16:11:11 -0400

> To: 	capozzi@math.mit.edu; duggins@math.mit.edu; juliec@mit.edu;
> mbj@mit.edu; daisymae@math.mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; seyferth@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 and possibly 4-371 and 382 Rescheduled Shutdown
> Request for 9/22
> 
> 
The following rescheduled shutdown request for Bldg. 2 and possibly
4-371 and 382 on 9/22 is for your information and comment. Would you
please let me know if this meets with your approval or does not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2 and possible 4-371 and 382
> Date: 9/22/98
> Day: Tuesday
> Time: 8:00 AM - 2:00 PM
> System: Chilled Water
> Duration: 6 hours
> Reason: 
> Tie-in new fan coil units in rooms 246A, 246B, 270, 272, 274, 278 and
> 280
> 
> Effect: 
> Loss air conditioning in all of Bldg. 2 and possibly Bldg. 4 - 371 and
> 382 during shutdown period..
> 
> 

home help back first fref pref prev next nref lref last post