[44961] in Hotline Meeting

home help back first fref pref prev next nref lref last post

FW: Bldg. 18 - ALL Air Handlers Shutdown Request for 9/20

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 17 11:26:44 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Thu, 17 Sep 1998 11:19:30 -0400

Oops--almost forgot to advise you of this--since it is the Chemistry
Dept. that would be involved --but they do have computers don't they.
Please let me know and thanks.
  Andrea

> ----------
> From: 	Andrea Nichols
> Sent: 	Friday, September 11, 1998 9:28 AM
> To: 	'juliec@mit.edu'; 'mbj@mit.edu'
> Cc: 	Shutdown
> Subject: 	Bldg. 18 - ALL Air Handlers Shutdown Request for 9/20
> Importance: 	High
> 
> > To: 	juliec@mit.edu; mbj@mit.edu
> > Cc: 	shutdown@plant.mit.edu
> > Subject: 	Bldg. 18 - ALL Air Handlers Shutdown Request for 9/20
> > 
> > 
> The following shutdown request for All Air Handlers for Bldg. 18 on
> 9/20
> is for your review and comment. Would you please let me know if this
> has
> your approval or does not.
> 
> Thanks very much.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 18
> > Date: 9/20/98
> > Day: Saturday
> > Time: 7 AM - 3 PM
> > System: All Air Handlers
> > Duration: 8 hours
> > Reason: 
> > Preventive maintenance - belt changes, bearings greased & checked,
> > shafts checked, motors checked, screens cleaned of leaves.
> > 
> > Effect: 
> > Loss of supply  ventilation, supply cooling and supply heating in
> all
> > of Bldg. 18. The shutdown for Air handlers 6 and 7 has already been
> > approved for 9/20 (that shutdown is from 6 AM to 6 PM).
> > 
> > 
> 

home help back first fref pref prev next nref lref last post