Bldg. 35 - 125A, 104, 106, 108, 110, 112 and 130 Asbestos Removal

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 15 15:49:13 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gerwent@mit.edu'" <gerwent@MIT.EDU>,
        "'stiffler@mit.edu'"
	 <stiffler@MIT.EDU>,
        "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'jfreeman@mit.edu'"
	 <jfreeman@MIT.EDU>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, "'tr6@mit.edu'" <tr6@MIT.EDU>,
        Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
        "'jdoucett@mit.edu'"
	 <jdoucett@MIT.EDU>,
        "'tdoyle@mit.edu'" <tdoyle@MIT.EDU>, B-Zone
	 <B-Zone@MIT.EDU>,
        "Larry St. John" <lstjohn@PLANT.MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        RM-Support
	 <RM-Support@MIT.EDU>
Date: Tue, 15 Sep 1998 15:41:44 -0400

> To: 	gerwent@mit.edu; stiffler@mit.edu; dcarlson@mit.edu;
> cappucci@mit.edu; jfreeman@mit.edu; cust-coach@mit.edu;
> mmahoney@mit.edu; tr6@mit.edu; Jack Narcotta; jdoucett@mit.edu;
> tdoyle@mit.edu; B-Zone; Larry St. John; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu; RM-Support
> Subject: 	Bldg. 35 - 125A, 104, 106, 108, 110, 112 and 130
> Asbestos Removal Notification for 9/18
> 
> 
The following asbestos removal notification for Bldg. 35 - 125A, 104,
106, 10-8, 110, 112 and 130 on 9/18 is for your information.  If you
have any questions about this, please contact Mr. Larry St. John at
3-6301 or 3-1500.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 35-125A, 104, 106, 108, 110, 112 and 130
> Date: 9/18/98
> Day: Friday
> Time: 2:00 PM - 10:00 PM
> System: None - asbestos removal notification only
> Duration: 8 hours
> Reason: 
> Asbestos removal notification - also to install new heating controls
> in preparation for this coming winter.
> 
> Effect: 
> Loss of use of the above listed  rooms during the asbestos removal
> period.
> 
> 