[44763] in Hotline Meeting
Bldg. 26 - 322 thru 328 (also entire 3rd floor) Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 2 14:39:19 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'gfp170@mitrlevm.mit.edu'"
<gfp170@mitrlevm.mit.edu>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 2 Sep 1998 14:32:29 -0400
> To: schedule@mit.edu; gfp170@mitrlevm.mit.edu; opsnote@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 26 - 322 thru 328 (also entire 3rd floor) Shutdown
> Request for 9/9
>
>
The following shutdown request for Bldg. 26 - 322 thru 328 (and also the
entire 3rd Floor) on 9/9 is for your information and comment. Would you
please let me know if this meets with your approval or does not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 26 - 322 thru 328 (also entire 3rd floor)
> Date: 9/9/98
> Day: Wednesday
> Time: 8:00 AM - 4:00 PM
> System: Chilled Water (air conditioning)
> Duration: 8 hours
> Reason:
> Feed in new branch lines to rooms 322 thru 328.
>
> Effect:
> This will affect the entire 3rd floor of Bldg.26 - (no air
> conditioning) during shutdown period.
>
>