[44760] in Hotline Meeting
FW:Approved - Update -- Bldgs. E17, E18 and E19 Emergency Power S
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 2 12:56:43 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'capucci@mit.edu'"
<capucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>,
Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
Dan Crovo <DCrovo@PLANT.MIT.EDU>, Joe Kay <jakay@PLANT.MIT.EDU>,
Carl Hagge <CHagge@PLANT.MIT.EDU>, MIS-Team <MIS-Team@PLANT.MIT.EDU>,
RM-2ndShift <rm-2ndshift@MIT.EDU>, Warren Scott <WScott@PLANT.MIT.EDU>,
Howard Harrison <HHarriso@PLANT.MIT.EDU>,
Steve Miscowski
<SMiscows@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
RM-Support
<RM-Support@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
Shirley DeWolfe <SDeWolfe@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Wed, 2 Sep 1998 12:49:50 -0400
The following approved Emergency Power shutdown for Bldgs. E17, E18 and
E19 on 9/3 PM is for your information.
Andrea Nichols
Operations Center
8-7872
> > Status: Routine
> > Building: E17, E18 and E19
> > Date: 9/3/98
> > Day: Thursday
> > Time: 8:00 PM - 10:00 PM
> > System: Emergency Power
> > Duration: 2 hours
> > Reason:
> > To make final connections to newly installed emergency generator.
> >
> > Effect:
> > E17 - No Power to Basement Corridor Lights; Animal Care Area - no
> exit
> > lights or emergency lights; No power to autocall equipment; No
> > elevators; Power to Freezers in Labs WILL be ON.
>
> E18 - no power to: stairwells, exit signs, some corridor
> > lights, receptables on emergency power, sump pump in recycling room,
> > elevators, FCS unit controllers.
>
> E19 - No power to stairwell lights,
> > exit signs, some corridor lights, receptacles on emergency power,
> FCS
> > unit controllers, outlets in Operations Center, fire alarm
> equipment,
> > outlets feeding some ethernet equipment for I.S., elevators. For
> IS:
> > Ethernet in E19 needs to remain ON for FCS.
>
>
>
>