RE:Update -- Bldgs. E17, E18 and E19 Emergency Power Shutdown Req

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 1 12:02:47 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: CAD-Admin <CAD-Admin@PLANT.MIT.EDU>, MIS-Admin
	 <mis-admin@PLANT.MIT.EDU>,
        MIS-Team <MIS-Team@PLANT.MIT.EDU>,
        Myers-Cup
	 <Myers-Cup@PLANT.MIT.EDU>,
        "'wardd@mit.edu'" <wardd@MIT.EDU>, "'rmelo@mit.edu'" <rmelo@MIT.EDU>,
        "'shyoung@mit.edu'" <shyoung@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'kelly@mit.edu'" <kelly@MIT.EDU>,
        Shirley DeWolfe
	 <SDeWolfe@PLANT.MIT.EDU>,
        "'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>,
        "'vryoung@mit.edu'" <vryoung@MIT.EDU>, "'amba@mit.edu'" <amba@MIT.EDU>,
        "'safety@mit.edu'" <safety@MIT.EDU>,
        "'farrell@mit.edu'"
	 <farrell@MIT.EDU>,
        "'cbunker@mit.edu'" <cbunker@MIT.EDU>,
        "'wbarrett@mit.edu'" <wbarrett@MIT.EDU>,
        "'edie@mitvmc.mit.edu'"
	 <edie@mitvmc.mit.edu>,
        "'dturn@mit.edu'" <dturn@MIT.EDU>, "'cashaw@mit.edu'" <cashaw@MIT.EDU>,
        "'kshooter@mit.edu'"
	 <kshooter@MIT.EDU>,
        "'lambert@mitvma.mit.edu'" <lambert@mitvma.mit.edu>,
        "'tmeehan@mit.edu'" <tmeehan@MIT.EDU>,
        "'opsnote@mit.edu'"
	 <opsnote@MIT.EDU>,
        "'sico@mit.edu'" <sico@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'honiker@mit.edu'"
	 <honiker@MIT.EDU>,
        "'kelley@mit.edu'" <kelley@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Tue, 1 Sep 1998 11:56:04 -0400

Dear Everyone:	
This shutdown request has been rescheduled to 8:00 - 10 PM on 9/3. Would
you please let me know if this new time meets with your approval or not.

Again thank you very much.

Andrea Nichols
Operations Center
8-7872

> > Status: Routine
> > Building: E17, E18 and E19
> > Date: 9/3/98
> > Day: Thursday
> > Time: 8:00 PM - 10:00 PM
> > System: Emergency Power
> > Duration: 2 hours
> > Reason: 
> > To make final connections to newly installed emergency generator.
> > 
> > Effect: 
> > E17 - Basement corridor lights; 6th floor animal care area: no exit
> > lights or emergency lights; No power to autocall equipment; No
> > elevators;
> 
>   E18 - no power to: stairwells, exit signs, some corridor
> > lights, receptables on emergency power, sump pump in recycling room,
> > elevators, FCS unit controllers. 
> 
>  E19 - No power to stairwell lights,
> > exit signs, some corridor lights, receptacles on emergency power,
> FCS
> > unit controllers, outlets in Operations Center, fire alarm
> equipment,
> > outlets feeding some ethernet equipment for I.S., elevators.  For
> IS:
> > Ethernet in E19 needs to remain ON for FCS.
>  
>  
> 