[44731] in Hotline Meeting
Bldgs. E17, E18 and E19 Emergency Power Shutdown Request for 9/3/
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 31 15:01:34 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: CAD-Admin <CAD-Admin@PLANT.MIT.EDU>, MIS-Admin
<mis-admin@PLANT.MIT.EDU>,
MIS-Team <MIS-Team@PLANT.MIT.EDU>,
Myers-Cup
<Myers-Cup@PLANT.MIT.EDU>,
"'wardd@mit.edu'" <wardd@MIT.EDU>, "'rmelo@mit.edu'" <rmelo@MIT.EDU>,
"'shyoung@mit.edu'" <shyoung@MIT.EDU>,
"'jmganno@mit.edu'" <jmganno@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'kelly@mit.edu'" <kelly@MIT.EDU>,
Shirley DeWolfe
<SDeWolfe@PLANT.MIT.EDU>,
"'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>,
"'vryoung@mit.edu'" <vryoung@MIT.EDU>, "'amba@mit.edu'" <amba@MIT.EDU>,
"'safety@mit.edu'" <safety@MIT.EDU>,
"'farrell@mit.edu'"
<farrell@MIT.EDU>,
"'cbunker@mit.edu'" <cbunker@MIT.EDU>,
"'wbarrett@mit.edu'" <wbarrett@MIT.EDU>,
"'edie@mitvmc.mit.edu'"
<edie@mitvmc.mit.edu>,
"'dturn@mit.edu'" <dturn@MIT.EDU>, "'cashaw@mit.edu'" <cashaw@MIT.EDU>,
"'kshooter@mit.edu'"
<kshooter@MIT.EDU>,
"'lambert@mitvma.mit.edu'" <lambert@mitvma.mit.edu>,
"'tmeehan@mit.edu'" <tmeehan@MIT.EDU>,
"'opsnote@mit.edu'"
<opsnote@MIT.EDU>,
"'sico@mit.edu'" <sico@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'honiker@mit.edu'"
<honiker@MIT.EDU>,
"'kelley@mit.edu'" <kelley@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 31 Aug 1998 14:54:43 -0400
> To: CAD-Admin; MIS-Admin; MIS-Team; Myers-Cup; wardd@mit.edu;
> rmelo@mit.edu; shyoung@mit.edu; jmganno@mit.edu; schedule@mit.edu;
> kelly@mit.edu; Shirley DeWolfe; jmedeiro@mit.edu; vryoung@mit.edu;
> amba@mit.edu; safety@mit.edu; farrell@mit.edu; cbunker@mit.edu;
> wbarrett@mit.edu; edie@mitvmc.mit.edu; dturn@mit.edu; cashaw@mit.edu;
> kshooter@mit.edu; lambert@mitvma.mit.edu; tmeehan@mit.edu;
> opsnote@mit.edu; sico@mit.edu; shutdowns@mit.edu; honiker@mit.edu;
> kelley@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. E17, E18 and E19 Emergency Power Shutdown Request
> for 9/3/98
>
>
The following emergency power shutdown request for Bldgs. E17, E18 and
E19 on 9/3 is for your review and comment. Would you please let me know
if this meets with your approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E17, E18 and E19
> Date: 9/3/98
> Day: Thursday
> Time: 5:00 PM - 7:00 PM
> System: Emergency Power
> Duration: 2 hours
> Reason:
> To make final connections to newly installed emergency generator.
>
> Effect:
> E17 - Basement corridor lights; 6th floor animal care area: no exit
> lights or emergency lights; No power to autocall equipment; No
> elevators; E18 - no power to: stairwells, exit signs, some corridor
> lights, receptables on emergency power, sump pump in recycling room,
> elevators, FCS unit controllers. E19 - No power to stairwell lights,
> exit signs, some corridor lights, receptacles on emergency power, FCS
> unit controllers, outlets in Operations Center, fire alarm equipment,
> outlets feeding some ethernet equipment for I.S., elevators. For IS:
> Ethernet in E19 needs to remain ON for FCS.
>
>