FW: Bldg. 1 - 132, 206, 214, 213, 207, 203 and 236 Shutdown Reque

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 19 10:41:36 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shtudowns@mit.edu'" <shtudowns@MIT.EDU>
Date: Wed, 19 Aug 1998 10:35:01 -0400

fYI and comment if any.
 Thanks. andrea

> ----------
> From: 	Andrea Nichols
> Sent: 	Thursday, August 13, 1998 11:03 AM
> To: 	Schedules Office; 'magowen@mit.edu'; 'patdixon@mit.edu'
> Cc: 	Shutdown
> Subject: 	Bldg. 1 - 132, 206, 214, 213, 207, 203 and 236 Shutdown
> Request for 8/25
> Importance: 	High
> 
> > To: 	schedules@mit.edu; magowen@mit.edu; patdixon@mit.edu
> > Cc: 	shutdown@plant.mit.edu
> > Subject: 	Bldg. 1 - 132, 206, 214, 213, 207, 203 and 236 Shutdown
> > Request for 8/25
> > 
> > 
> The following shutdown request for Bldg. 1 - (see above room listings)
> on 8/25 is for your review and  comment. Would you please let me know
> if
> this meets with your approval or does not.
> 
> Thank you.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 132, 206, 214, 213, 207, 203, 236
> > Date: 8/25/98
> > Day: Tuesday
> > Time: 8:00 AM - 12 Noon
> > System: Chilled Water
> > Duration: 4 hours
> > Reason: 
> > Tie-in newly installd fan coil unit in Room 1-236 (Spofford
> Conference
> > Room).
> > 
> > Effect: 
> > Loss of chilled water (air conditioning) in 132, 206, 214, 213, 207,
> > 203 and 236 during 4-hour shutdown period.
> > 
> > 
> 