[44560] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Revised -Bldgs. 5, 7, E52, E53 and E55 All Normal Electric Po

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 19 09:00:23 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'mgibson@mit.edu'"
	 <mgibson@MIT.EDU>,
        "'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
        "'sburke@mit.edu'" <sburke@MIT.EDU>,
        "'skendall@mit.edu'"
	 <skendall@MIT.EDU>,
        "'altonero@mit.edu'" <altonero@MIT.EDU>,
        "'jsmith@mit.edu'" <jsmith@MIT.EDU>, "'mleen@mit.edu'" <mleen@MIT.EDU>,
        "'mamullow@mit.edu'" <mamullow@MIT.EDU>, "'ndk@mit.edu'" <ndk@MIT.EDU>,
        "'decarli@mit.edu'" <decarli@MIT.EDU>,
        "'patdixon@mit.edu'"
	 <patdixon@MIT.EDU>,
        "'kbarrett@mit.edu'" <kbarrett@MIT.EDU>,
        "'rdavies@mit.edu'" <rdavies@MIT.EDU>,
        "'cwilkes@mit.edu'"
	 <cwilkes@MIT.EDU>,
        "'rhwill@mit.edu'" <rhwill@MIT.EDU>, "'src@mit.edu'"
	 <src@MIT.EDU>,
        "'jobrien@mit.edu'" <jobrien@MIT.EDU>,
        "'engler@mitvma.mit.edu'" <engler@mitvma.mit.edu>,
        "'cod@mit.edu'"
	 <cod@MIT.EDU>, "'lhill@mit.edu'" <lhill@MIT.EDU>,
        "'mscoppa@mit.edu'"
	 <mscoppa@MIT.EDU>,
        "'michaela@mit.edu'" <michaela@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
        "'maureen@mit.edu'" <maureen@MIT.EDU>,
        "'jbkalb@mit.edu'" <jbkalb@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
        "'janets@mit.edu'" <janets@MIT.EDU>,
        "'mwhelan@mit.edu'"
	 <mwhelan@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
        "'melanie@mit.edu'"
	 <melanie@MIT.EDU>,
        "'lreinher@mit.edu'" <lreinher@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 19 Aug 1998 08:54:08 -0400

Dear Everyone:
Please note the revisions in the type of services affected section of
this shutdown request for this coming Friday, 8/21. If you have a
concern about this, please let me know by the end of today, if at all
possible.

Thank you for your time and I look foward to hearing from you. 

Andrea Nichols
Operations Center
8-7872

> ----------
> The following all normal electric power shutdown request for buildings
> 5, 7, E52, E53 and E55 on 8/21 is for your information and comment.
> Would you please let me know if this has your approval or not.
> 
> 
> > Status: Normal
> > Building: 5, 7, E52, E53 and E55
> > Date: 8/21/98
> > Day: Friday
> > Time: 5:00 AM - 6:00 AM
> > System: All Normal Electric Power
> > Duration: 1/2 hour between above times
> > Reason: 
> > Final loop phase check at power plant.
> > 
> > Effect: 
> > Loss of power: building, elevators, computers and lighting;
> Buildings
> > will have emergency power. Water: Loss of chilled water (air
> conditioning);  Air:  Supply ventilation, supply cooling, exhaust
> general, exhaust-toilet, compressed control air;  Steam:  condensate
> return.
> > 
> > 
> 

home help back first fref pref prev next nref lref last post