RE: Bldg. E52 Critical Shutdown Request for 6/12 and 13

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 10 15:20:54 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'lhill@mit.edu'" <lhill@MIT.EDU>, "'gwj@mit.edu'"
	 <gwj@MIT.EDU>,
        "'maureen@mit.edu'" <maureen@MIT.EDU>,
        "'jbkalb@mit.edu'"
	 <jbkalb@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, RM-Support <RM-Support@MIT.EDU>,
        E-Zone <E-Zone@MIT.EDU>
Date: Wed, 10 Jun 1998 15:16:52 -0400

Hello All:
I have been informed that it is critical  the shutdown request for Bldg.
E52 on 6/12 and 6/13 remain as originally sent. If you have a concern
about this, please contact Mr. Warren Scott at 3-6328 or Mr. Paul
Motroni at 2-1497.

Thank you for your patience.

Andrea Nichols
Operations Center
8-7872
> ----------
> > Status: Critical
> > Building: E52
> > Date: 6/12/13
> > Day: Friday PM and Saturday PM
> > Time: 4:00 PM - 4:00 PM
> > System: Air Handler 1 (supply ventilation, supply cooling)
> > Duration: 24 hours
> > Reason: 
> > Repair condensate pan. (This is leaking and must be repaired).
> > 
> > Effect: 
> > Loss of supply ventilation and supply cooling during 24-hour
> shutdown.
> > 
> > 
> 