[43787] in Hotline Meeting
RE: Bldg. E52 Emergency Shutdown for 6/14 that will also affect B
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 10 12:11:29 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'dbarber@mit.edu'" <dbarber@MIT.EDU>,
Dan Gustafson
<dgustafs@PLANT.MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
"'maureen@mit.edu'" <maureen@MIT.EDU>,
"'jbkalb@mit.edu'"
<jbkalb@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'dwp@mit.edu'" <dwp@MIT.EDU>, "'dlbrooks@mit.edu'" <dlbrooks@MIT.EDU>,
"'jstein@mit.edu'" <jstein@MIT.EDU>,
"'dbarber@mit.edu'"
<dbarber@MIT.EDU>,
"'dempsey@mit.edu'" <dempsey@MIT.EDU>, "'nlux@mit.edu'" <nlux@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, RM-Support <RM-Support@MIT.EDU>,
Cust-Coach <cust-coach@MIT.EDU>
Date: Wed, 10 Jun 1998 12:07:27 -0400
Dear Everyone:
I have just been advised that the Emergency shutdown for Bldg.
E52 on 6/14 will also affect Bldg. E51 (possibly), and definitely affect
buildings E56 and E60. If you have any questions about this, please
contact Dave Barber at 3-8022. This work is at the request of the City
of Cambridge. I have already spoken to a member of the Faculty Club,
this is all right with them.
Andrea Nichols
Operations Center
8-7872
> > Status: Emergency
> > Building: E52
> > Date: 6/14/98
> > Day: Sunday
> > Time: 7:00 AM - 3:00 PM or longer
> > System: Cold and Hot Domestic Water
> > Duration: 8 hours or more
> > Reason:
> > Replace main gate valves coming into building E52.
> >
> > Effect:
> > Loss of cold and hot domestic water. This means that all kitchens,
> > bathrooms, water coolers will not be operating during the shutdown
> > period.
> >
> >
>