[43748] in Hotline Meeting
Blg. E52 Critical Shutdown Request for 6/12 and 13
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 8 14:18:02 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>, "'gwj@mit.edu'"
<gwj@MIT.EDU>,
"'maureen@mit.edu'" <maureen@MIT.EDU>,
"'jbkalb@mit.edu'"
<jbkalb@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Mon, 8 Jun 1998 14:13:56 -0400
> To: schedule@mit.edu; shutdowns@mit.edu; lhill@mit.edu; gwj@mit.edu;
> maureen@mit.edu; jbkalb@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Blg. E52 Critical Shutdown Request for 6/12 and 13
>
>
The following Critical shutdown request for Bldg. E52 on 6/12 and 6/13
is for your information and comment. Would you please let me know if
this meets with your approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E52
> Date: 6/12/13
> Day: Friday
> Time: 4:00 PM - 4:00 PM
> System: Air Handler 1 (supply ventilation, supply cooling)
> Duration: 24 hours
> Reason:
> Repair condensate pan. (This is leaking and must be repaired).
>
> Effect:
> Loss of supply ventilation and supply cooling during 24-hour shutdown.
>
>