[43596] in Hotline Meeting
RE: Rescheduled - Building 50 - All Electrical Shutdown Request f
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 27 11:46:17 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'mwf@mit.edu'" <mwf@MIT.EDU>, "'nmosley@mit.edu'"
<nmosley@MIT.EDU>,
"'eisen@mit.edu'" <eisen@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
Manuel Moreira
<mmoreira@PLANT.MIT.EDU>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
"'graposa@mit.edu'" <graposa@MIT.EDU>
Date: Wed, 27 May 1998 11:42:42 -0400
Dear Everyone:
Because of a mix-up in dates--this All Electrical shutdown request for
Bldg. 50 has been rescheduled to Friday, 5/29. This means that the
previous night would be Thursday, 5/28. The shutdown would begin at
12:01 AM on Friday, 5/29. If you have a concern about this, please
contact me. If I don't hear from you I will assume that this new date
meets with your approval.
Thank you very much for your patience in this matter.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: 50 - All Except for Main Kitchen)
> > Date: 5/29/98
> > Day: Friday
> > Time: 12:01 AM - 8:00 AM
> > System: Electrical
> > Duration: 8 hours
> > Reason:
> > To move existing electrical panel in 50-010.
> >
> > Effect:
> > Loss of Power: access controls, building power, elevators,
> computers,
> > lighting; Air: supply ventilation, supply cooling, supply heating,
> > exhaust general air and exhaust toilet air;
> >
> >
>