[43566] in Hotline Meeting
RE: Correction --Rescheduled- Building 50 - All Electrical Shutdo
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 26 08:41:24 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'mwf@mit.edu'" <mwf@MIT.EDU>, "'eisen@mit.edu'"
<eisen@MIT.EDU>,
"'nmasley@mit.edu'" <nmasley@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
"'graposa@plant.mit.edu'"
<graposa@plant.mit.edu>,
Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
Manuel Moreira
<mmoreira@PLANT.MIT.EDU>, A-Zone <A-Zone@MIT.EDU>
Date: Tue, 26 May 1998 08:37:49 -0400
Dear Everyone: I have been informed by the project manager that this
shutdown is for Thursday AM (5/28) not Wednesday. In other words it
would take place at 12:01 AM on Thursday (after Wednesday evening).
If this presents a problem, please let me know. Otherwise I will assume
that the corrected date is all right with you.
Thank you.
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 50 - All Except for Main Kitchen)
> > Date: 5/28/98
> > Day: Thursday
> > Time: 12:01 AM - 8:00 AM
> > System: Electrical
> > Duration: 8 hours
> > Reason:
> > To move existing electrical panel in 50-010.
> >
> > Effect:
> > Loss of Power: access controls, building power,
> elevators, computers,
> > lighting; Air: supply ventilation, supply cooling,
> supply heating,
> > exhaust general air and exhaust toilet air;
> >
> >
>
>
>