RE: Bldg. 12 and 12A Shutdown Request for TBD
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 25 13:41:58 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jcentor@mit.edu'" <jcentor@MIT.EDU>,
"'jbartels@mit.edu'"
<jbartels@MIT.EDU>,
"'jsmith@mit.edu'" <jsmith@MIT.EDU>,
"'bkaynor@mit.edu'" <bkaynor@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'genh@mit.edu'" <genh@MIT.EDU>, "'zqueen@mit.edu'" <zqueen@MIT.EDU>,
"'kblass@mit.edu'" <kblass@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
"'varela@plant.mit.edu'"
<varela@plant.mit.edu>,
Warren Scott <WScott@PLANT.MIT.EDU>
Date: Wed, 25 Mar 1998 13:40:24 -0500
Update --3/25
Dear Everyone:
I has been requested that this shutdown be postponed until sometime
next week. As soon as I have another date I will be forward this
information on to you.
Thank you for your patience.
Andrea Nichols
Operations Center
8-7872
> ----------
> From: Andrea Nichols
> Sent: Monday, March 23, 1998 3:05 PM
> To: 'jcentor@mit.edu'; 'jbartels@mit.edu'; 'jsmith@mit.edu';
> 'bkaynor@mit.edu'; 'schedule@mit.edu'; 'shutdowns@mit.edu';
> 'genh@mit.edu'; 'zqueen@mit.edu'; 'kblass@mit.edu'
> Cc: Shutdown
> Subject: Bldg. 12 and 12A Shutdown Request for 3/26
> Importance: High
>
> The following shutdown request for Bldgs. 12 and 12A originally
> requested for 3/26 has been postponed.
>
> > Status: Normal
> > Building: 12 and 12A
> > Date: 3/TBD/98
> > Day: TBD
> > Time: 5:00 PM - 10:00 PM
> > System: Domestic hot and cold water; hot and cold lab process water
> > Duration: 5 hours
> > Reason:
> > Tie-in of containment backflow preventer.
> >
> > Effect:
> > Loss of hot and cold domestic water (no restroom, kitchen facilities
> > and drinking fountains; loss of hot and cold lab process water (no
> lab
> > water available for experiments.)
> >
> >
>