[42429] in Hotline Meeting
FW:Approved - Bldg. 6 - 132, 134, 136, Panel DP-1 Electrical Shut
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 16 15:40:15 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'cust-coach@mit.edu'"
<cust-coach@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
Greg Raposa
<graposa@PLANT.MIT.EDU>,
Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
Manuel Moreira
<mmoreira@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
RM-Support
<RM-Support@MIT.EDU>, "'juliec@mit.edu'" <juliec@MIT.EDU>,
"'mbj@mit.edu'" <mbj@MIT.EDU>, "'tidor@mit.edu'" <tidor@MIT.EDU>,
Warren Scott <WScott@PLANT.MIT.EDU>
Date: Mon, 16 Mar 1998 15:38:26 -0500
The following approved shutdown for Bldg. 6 - 132, 134, 136 Panel DP-1
Electrical 208V, 110V on 3/19 PM - 3/20 AM is for your information.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: 6 - 132, 134, 136 & Panel DP-1
> > Date: 3/19/20
> > Day: Thursday PM - Friday AM
> > Time: 11:00 PM - 7:00 AM
> > System: Electrical - 208V, 110V. Electrical power outlets and fan
> coil units located in 124, 126A, 123, 125, 128A, 128, 127, 130, 127,
> 132, 131, 134, 133 and 138
> > Duration: 8 hours
> > Reason:
> > To tie in new 250 A circuit breaker to 208V buss duct riser by
> outside contractor.
> >
> > Effect:
> > Loss of Bldg. power (supply ventilation), computers, lighting during
> > shutdown period.
> >
> >
>
>