Bldg. 2 and Laser Labs 067, 065, 063 and 069 Shutdown Request for

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 4 16:19:34 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'capozzi@mit.edu'" <capozzi@MIT.EDU>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
        "'duggins@mit.edu'" <duggins@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 4 Mar 1998 16:18:39 -0500

> To: 	shutdowns@mit.edu; schedule@mit.edu; capozzi@mit.edu;
> juliec@mit.edu; mbj@mit.edu; duggins@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 and Laser Labs 067, 065, 063 and 069 Shutdown
> Request for 3/14
> 
> 
The following shutdown request for Bldg. 2 and laser labs 067, 065, 063
and 069 on 3/14 is for your review and comment. Would you please let me
know if this has your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2 and 067, 065, 063 & 069
> Date: 3/14/98
> Day: Saturday
> Time: 8:00 AM - 12 Noon
> System: Chilled water 
> Duration: 4 hours
> Reason: 
> To install relays for speed drive for chilled water pump 2 to run off
> drive.
> 
> Effect: 
> Loss of chilled water in bldg. This means that there will be no air
> conditioning and no water to cool lasers in above mentioned rooms.
> 
> 