[42175] in Hotline Meeting
RE: Approved -W91 - All - Electric Power and lighting Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 2 15:38:29 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
James Sullivan
<jsulliva@PLANT.MIT.EDU>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
RM-Support <RM-Support@MIT.EDU>, "'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'shutdown@mit.edu'" <shutdown@MIT.EDU>
Date: Mon, 2 Mar 1998 15:34:09 -0500
Dear Everyone--
Update--this shutdown is for Thursday, 3/5 not Friday 3/5. Sorry for the
confusion.
Andrea Nichols
> ----------
> From: Andrea Nichols
> Sent: Monday, March 2, 1998 12:14 PM
> To: 'dcarlson@mit.edu'; 'cappucci@mit.edu'; 'jfreeman@mit.edu';
> 'mmahoney@mit.edu'; D-Zone; Neil Tomlinson; James Sullivan; Manuel
> Moreira
> Cc: Shutdown; Cust-Coach; RM-Support; 'opsnote@mit.edu';
> 'shutdown@mit.edu'
> Subject: FW: Approved -W91 - All - Electric Power and lighting
> Shutdown Request for 3/5 PM
>
> The following approved Electric Power and Lighting Shutdown for Bldg.
> W91 on 3/5 is for your information.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > > Status: Normal
> > > Building: W91 - All
> > > Date: 3/5/98
> > > Day: Friday
> > > Time: 5:00 PM - 10:00 PM
> > > System: All electric power and lighting (new UPS will power the
> main
> > > machine room)
> > > Duration: 5 hours
> > > Reason:
> > > To test new electrical switchgear and emergency generator.
> > >
> > > Effect:
> > > Loss of Power: access controls, bldg. power, elevators, computers,
> > > telephones and lighting; Water: chilled water and condenser water:
> > Emergency Power will remain on as will lighting for corridors and
> > stairs.
> > > Air: supply ventilation, supply cooling, supply heating, exhaust
> > > general, exhaust toilet and compressed control air; Steam:
> > condensate
> > > return.
> > >
> > >
> >
>