[42091] in Hotline Meeting
Bldgs. 6 and 8 Shutdown Request for 2/26
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 25 12:23:14 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'juliec@mit.edu'" <juliec@MIT.EDU>,
"'acherron@mit.edu'"
<acherron@MIT.EDU>,
"'naylor@mit.edu'" <naylor@MIT.EDU>, "'elp@mit.edu'"
<elp@MIT.EDU>,
"'farideh@mit.edu'" <farideh@MIT.EDU>,
"'carolr@mit.edu'"
<carolr@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 25 Feb 1998 12:22:29 -0500
> To: schedule@mit.edu; shutdowns@mit.edu; adams@mitlns.mit.edu;
> juliec@mit.edu; acherron@mit.edu; naylor@mit.edu; elp@mit.edu;
> farideh@mit.edu; carolr@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 6 and 8 Shutdown Request for 2/26
>
>
The following shutdown request for Bldgs. 6 and 8 on 2/26 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 6 and 8
> Date: 2/26/98
> Day: Thursday
> Time: 7:00 AM - 9:00 AM
> System: Hot domestic water (kitchen and bathroom faucets)
> Duration: 2 hours
> Reason:
> Add shower eye washer unit to 8-003
>
> Effect:
> Loss of hot domestic water only. The line that is will be tied into
> affects hot domestic water only - cold water will remain on.
>
>