[42089] in Hotline Meeting
Bldg. E51 - Entire Bldg. 2/28 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 25 12:13:36 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sschedule@mit.edu'" <sschedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>,
"'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
"'dlbrooks@mit.edu'"
<dlbrooks@MIT.EDU>,
"'jstein@mit.edu'" <jstein@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 25 Feb 1998 12:12:58 -0500
> To: sschedule@mit.edu; shutdowns@mit.edu; lhill@mit.edu;
> mdimauro@mit.edu; dlbrooks@mit.edu; jstein@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E51 - Entire Bldg. 2/28 Shutdown Request
>
>
The following shutdown request for Bldg. E51 on 2/28 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E51
> Date: 2/28/98
> Day: Saturday
> Time: 6:00 AM - 12 Noon
> System: Hot Domestic Water - (bathroom and kitchen faucets only)
> Duration: 6 hours or asap
> Reason:
> To install check valves - hot water getting into cold water.
>
> Effect:
> Loss of hot domestic water during shutdown period. This would affect
> bathroom and kitchen faucets only.
>
>