[42089] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. E51 - Entire Bldg. 2/28 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 25 12:13:36 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sschedule@mit.edu'" <sschedule@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'lhill@mit.edu'" <lhill@MIT.EDU>,
        "'mdimauro@mit.edu'" <mdimauro@MIT.EDU>,
        "'dlbrooks@mit.edu'"
	 <dlbrooks@MIT.EDU>,
        "'jstein@mit.edu'" <jstein@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 25 Feb 1998 12:12:58 -0500

> To: 	sschedule@mit.edu; shutdowns@mit.edu; lhill@mit.edu;
> mdimauro@mit.edu; dlbrooks@mit.edu; jstein@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E51 - Entire Bldg. 2/28 Shutdown Request
> 
> 
The following shutdown request for Bldg. E51 on 2/28 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: E51
> Date: 2/28/98
> Day: Saturday
> Time: 6:00 AM - 12 Noon
> System: Hot Domestic Water - (bathroom and kitchen faucets only)
> Duration: 6 hours or asap
> Reason: 
> To install check valves - hot water getting into cold water.
> 
> Effect: 
> Loss of hot domestic water during shutdown period. This would affect
> bathroom and kitchen faucets only.
> 
> 