Blg. 24 Shutdown Request for 3/2
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Feb 24 12:22:14 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'adams@mitlns.mit.edu'"
<adams@mitlns.mit.edu>,
"'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
"'elices@mit.edu'" <elices@MIT.EDU>,
"'devries@mit.edu'"
<devries@MIT.EDU>,
"'hbsweet@mit.edu'" <hbsweet@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 24 Feb 1998 12:21:28 -0500
> To: schedule@mit.edu; adams@mitlns.mit.edu; rroscoe@mit.edu;
> elices@mit.edu; devries@mit.edu; hbsweet@mit.edu; opsnote@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Blg. 24 Shutdown Request for 3/2
>
>
The following shutdown request for Bldg. 24 on 3/2 is for your review
and comment. Would you please let me know if this has your approval or
not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 24
> Date: 3/2/98
> Day: Monday
> Time: 3:00 PM - 11:00 PM
> System: Medium Pressure Steam affecting hot domestic and heating hot
> water
> Duration: 8 hours
> Reason:
> Construction project - tie-in new units.
>
> Effect:
> Loss of hot domestic (kitchen & bathroom faucets) and heating hot
> water during shutdown.
>
>