[41914] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 9 - Shutdown Rquest for 2/20/98

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Feb 17 11:51:05 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'westlund@mit.edu'" <westlund@MIT.EDU>,
        "'rengler@mitvma.mit.edu'"
	 <rengler@mitvma.mit.edu>,
        "'annab@mit.edu'" <annab@MIT.EDU>,
        "'cwilkes@mit.edu'" <cwilkes@MIT.EDU>,
        "'chambe@mit.edu'"
	 <chambe@MIT.EDU>,
        "'jobrien@mit.edu'" <jobrien@MIT.EDU>,
        "'mshiffer@mit.edu'" <mshiffer@MIT.EDU>,
        "'opsnote@mit.edu'"
	 <opsnote@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 17 Feb 1998 11:50:33 -0500

> To: 	westlund@mit.edu; rengler@mitvma.mit.edu; annab@mit.edu;
> cwilkes@mit.edu; chambe@mit.edu; jobrien@mit.edu; mshiffer@mit.edu;
> opsnote@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 9 - Shutdown Rquest for 2/20/98
> 
> 
The following shutdown request for Bldg. 9 on 2/20 is for your
information and comment. Would you please let me know if this has your
approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 9
> Date: 2/20/98
> Day: Friday
> Time: 6:00 PM - 12 Midnight
> System: Building Power - 480V entire switchgear -- 208120V Switchgear
> is ON
> Duration: 6 hours
> Reason: 
> Installl new breaker in switchgear
> 
> Effect: 
> Loss of building power, all mechanical equipment (fans, pumps, etc.)
> elevators, lighting; Water:  chilled water, heating hot water; Air:
> supply ventilation, supply cooling, supply heating,
> exhaust-laboratory, exhaust-general, exhaust-toilet, compressed
> control, compressed lab ir and lab vacuum air; Steam:  condensate
> return. Loss of all lighting. (Emergency power WILL be on - corridor,
> stairs, exits lights - all on.)
> 
> Floors 1 thru 4 will have 120V outlets.
> 5th Floor will lose most 120V power also - it is fed from 480V
> transformer).
> 
> 