Bldg. 1 - 3rd Floor (North Wing) Shutdown Request for 1/13/98

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Feb 10 13:37:41 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdown@mit.edu'"
	 <shutdown@MIT.EDU>,
        "'pmccosco@mit.edu'" <pmccosco@MIT.EDU>,
        "'magowen@mit.edu'" <magowen@MIT.EDU>,
        "'patdixon@mit.edu'"
	 <patdixon@MIT.EDU>,
        "'mamullow@mit.edu'" <mamullow@MIT.EDU>,
        "'mgibson@mit.edu'" <mgibson@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 10 Feb 1998 13:36:28 -0500

> To: 	schedule@mit.edu; shutdown@mit.edu; pmccosco@mit.edu;
> magowen@mit.edu; patdixon@mit.edu; mamullow@mit.edu; mgibson@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1 - 3rd Floor (North Wing) Shutdown Request for
> 1/13/98
> 
> 
The following shutdown request for Bldg. 1 - 3rd Floor - North Wing on
1/13 is for your information and comment. Would you please let me know
if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 1 - 3rd Floor - North Wing
> Date: 1/13/98
> Day: Friday
> Time: 8:00 AM - 2:00 PM
> System: Chilled Water
> Duration: 6 hours
> Reason: 
> Tie-in Fan Coil Units
> 
> Effect: 
> Loss of air conditioning in 3rd floor North Wing rooms - example of
> rooms that would be affected are Rooms 341A, 343, etc. 
> 
> 