[41646] in Hotline Meeting
RE: To be Rescheduled -- Approved - Bldg. 66 Shutdown Request to
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jan 28 15:43:16 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'lindlore@mit.edu'" <lindlore@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
"'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
Cust-Coach
<cust-coach@MIT.EDU>,
"'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, A-Zone
<A-Zone@MIT.EDU>,
"'sdverify@mit.edu'" <sdverify@MIT.EDU>,
Dan Gustafson
<dgustafs@PLANT.MIT.EDU>,
Phil Donaghey <pdonaghe@PLANT.MIT.EDU>
Date: Wed, 28 Jan 1998 15:43:25 -0500
Hi Linda,
Have you heard anything about this shutdown request for 2/1 yet?
Would you please let me know if this new date would be all right --or
not.
> Thanks again.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> ----> Status: Normal
> > > Building: 66 - all labs, restroom facilities, kitchen
> faucets,
> > > drinking fountains, emergency showers
> > > Date: 2/01/98
> > > Day: Sunday
> > > Time: 6:00 AM - 2:00 PM or more or less
> > > System: ALL water, domestic hot and cold, pure water, hot
> and cold
> > lab
> > > process and de-ionized
> > > Duration: 8 hours or longer or less
> > > Reason:
> > > Replace defective gate valves and pressure reducing valves
> in the
> > > building
> > >
> > > Effect:
> > > Loss of ALL water systems in the building from 6:00 AM -
> 2:00 PM or
> > > more or less.
> > > This means that there will be no restrooms, kitchen,
> showers, lab
> > water and drinking fountains that will be operational during
> this
> > shutdown period.
> > >
> >
>
>