[41643] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. NW22 - 1/28-PM - 29 AM Emergency Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jan 28 15:29:28 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'hrycaj@pfc.mit.edu'" <hrycaj@PSFC.MIT.EDU>,
        "'fulton@psfc.mit.edu'"
	 <fulton@psfc.mit.edu>,
        D-Zone <D-Zone@MIT.EDU>, "'dcarlson@mit.edu'"
	 <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
        "'jfreeman@mit.edu'"
	 <jfreeman@MIT.EDU>, D-Zone <D-Zone@MIT.EDU>,
        "'sdverify@mit.edu'"
	 <sdverify@MIT.EDU>,
        Paul McCafferty <pmccaffe@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Date: Wed, 28 Jan 1998 15:27:51 -0500

> To: 	hrycaj@pfc.mit.edu; fulton@psfc.mit.edu; D-Zone;
> dcarlson@mit.edu; cappucci@mit.edu; mmahoney@mit.edu;
> jfreeman@mit.edu; D-Zone; sdverify@mit.edu; Paul McCafferty
> Cc: 	shutdown@plant.mit.edu; cust-coach@mit.edu; shutdowns@mit.edu
> Subject: 	Bldg. NW22 - 1/28-PM - 29 AM Emergency Shutdown
> 
> 
The following emergency shutdown for Bldg. NW22 from 1/28 PM to 1/29 AM
is for your information.  

Andrea Nichols
Operations Center
8-7872

> Status: Emergency
> Building: NW22
> Date: 1/28/29
> Day: Wednesday
> Time: 2:30 PM - 9:30 AM
> System: Heating
> Duration: 19 hours
> Reason: 
> Parts ordered for this emergency shutdown (did not  have particular
> heating system replacement part in-house)
> 
> Effect: 
> None - heating system not operational - should be operational at 9:30
> AM on 1/29.
> 
> 