FW:Approved - Bldg. 66 Shutdown Request for 1/25
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 22 15:01:11 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cappucci@mit.edu'"
<cappucci@MIT.EDU>,
"'jfreeman@mit.edu'" <jfreeman@MIT.EDU>,
"'cust-coach@mit.edu'" <cust-coach@MIT.EDU>,
"'mmahoney@mit.edu'"
<mmahoney@MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
"'sdverify@mit.edu'"
<sdverify@MIT.EDU>,
Dan Gustafson <dgustafs@PLANT.MIT.EDU>,
Phil Donaghey <pdonaghe@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Thu, 22 Jan 1998 15:01:25 -0500
The following approved shutdown for Bldg. 66 on 1/25 is for your
information.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> > Building: 66 - all labs, restroom facilities, kitchen faucets,
> > drinking fountains, emergency showers
> > Date: 1/25/98
> > Day: Sunday
> > Time: 6:00 AM - 2:00 PM or more or less
> > System: ALL water, domestic hot and cold, pure water, hot and cold
> lab
> > process and de-ionized
> > Duration: 8 hours or longer or less
> > Reason:
> > Replace defective gate valves and pressure reducing valves in the
> > building
> >
> > Effect:
> > Loss of ALL water systems in the building from 6:00 AM - 2:00 PM or
> > more or less.
> > This means that there will be no restrooms, kitchen, showers, lab
> water and drinking fountains that will be operational during this