[41523] in Hotline Meeting
Bldg. 56 - Floors 1 thru 7 Sprinkler Shutdown Request for 1/23, 2
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jan 20 16:14:27 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'loudib@mit.edu'" <loudib@MIT.EDU>,
"'claudia@mit.edu'" <claudia@MIT.EDU>,
"'bmalone@mit.edu'"
<bmalone@MIT.EDU>,
"'lindlore@mit.edu'" <lindlore@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'juliec@mit.edu'" <juliec@MIT.EDU>, "'rha@mit.edu'" <rha@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
Kenneth Polito
<kpolito@PLANT.MIT.EDU>,
"'sdverify@mit.edu'" <sdverify@MIT.EDU>, A-Zone
<A-Zone@MIT.EDU>,
Howard Harrison <HHarriso@PLANT.MIT.EDU>,
Brian Winsor <bcwinsor@PLANT.MIT.EDU>
Date: Tue, 20 Jan 1998 16:14:48 -0500
> To: shutdowns@mit.edu; schedule@mit.edu; loudib@mit.edu;
> claudia@mit.edu; bmalone@mit.edu; lindlore@mit.edu; mbj@mit.edu;
> juliec@mit.edu; rha@mit.edu
> Cc: shutdown@plant.mit.edu; Kenneth Polito; sdverify@mit.edu;
> A-Zone; Howard Harrison; Brian Winsor
> Subject: Bldg. 56 - Floors 1 thru 7 Sprinkler Shutdown Request
> for 1/23, 26 and 27
>
>
The following Sprinkler shutdown request for Bldg. 56 floors 1 thru 7 on
1/23, 26 and 27 is for your information.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 56 - floors 1 thru 7
> Date: 1/23/98
> Day: Friday
> Time: 7:30 AM - 2:30 PM each day
> System: Sprinkler (Fire Protection Water)
> Duration: 8 hours each day
> Reason:
> Complete Phase III of adding sprinklers to conference rooms
>
> Effect:
> Loss of fire protection water during shutdown. The Safety Office has
> been advised of this. That office if need be will contact the Fire
> Department.
>
>