[41313] in Hotline Meeting
RE: Rescheduling Request Bldg. 56 Shutdown Request now on 1/5/98
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Dec 30 10:04:45 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: mparker@MIT.EDU, mbj@MIT.EDU, juliec@MIT.EDU, jmganno@MIT.EDU, rca@MIT.EDU,
swetzel@MIT.EDU, loudib@MIT.EDU, claudia@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU, pguyer@MIT.EDU, crha@MIT.EDU, bmalone@MIT.EDU,
Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Tue, 30 Dec 1997 10:02:49 -0500
Dear Everyone...I sent an email about this rescheduling request to you
yesterday but for some reason it did not go through to you. Here is the
request again and I look forward to hearing from you.
Thank you again.
Andrea Nichols
> ----------
It has been requested that the following shutdown request for
Bldg. 56 be rescheduled to 1/5/98. Would you please let me know if this
new date has your
> approval or not.
>
> Thanks very much.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 56 (entire bldg.)
> > Date: 1/5/98
> > Day: Monday
> > Time: 6:00 AM - 10:00 AM
> > System: Chilled Water (air conditioning, equipment cooling, R.
> O./De-ionized water
> > Duration: 4 hours
> > Reason: R. O. D. I. System out of service
> > Repair a valve on main chilled water line to building
> >
> > Effect:
> > Loss of all systems using chilled water; air conditioning, equipment
> > cooling (All Air Handler Units including AH #4).
> >
> >
>