Bldg. 11 Shutdown Request for 12/25

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Dec 19 13:22:37 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'graham@mit.edu'" <graham@MIT.EDU>, "'jean@mit.edu'" <jean@MIT.EDU>,
        "'hogue@mit.edu'" <hogue@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'rhwill@mit.edu'" <rhwill@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 19 Dec 1997 13:20:42 -0500

> To: 	graham@mit.edu; jean@mit.edu; hogue@mit.edu; shutdowns@mit.edu;
> rhwill@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 11 Shutdown Request for 12/25
> 
> 
The following shutdown request for Bldg. 11 on 12/25 is for your
informtion and comment. Would you please let me know if this has your
approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 11 (entire bldg.)
> Date: 12/25/97
> Day: Thursday
> Time: 8:00 AM - 2:00 PM
> System: Air: supply ventilation, cooling and heating
> Duration: 6 hours
> Reason: 
> Preventive maintenance on Air Handlers 1, 2, 3 and 5
> 
> Effect: 
> Minimal  loss of supply and return ventilation, cooling and heating.
> Each Air Handler wil be down one at a time while the others remain
> operational.
> 
> 