[41260] in Hotline Meeting
Bldg. 11 Shutdown Request for 12/25
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Dec 19 13:22:37 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'graham@mit.edu'" <graham@MIT.EDU>, "'jean@mit.edu'" <jean@MIT.EDU>,
"'hogue@mit.edu'" <hogue@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'rhwill@mit.edu'" <rhwill@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 19 Dec 1997 13:20:42 -0500
> To: graham@mit.edu; jean@mit.edu; hogue@mit.edu; shutdowns@mit.edu;
> rhwill@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 11 Shutdown Request for 12/25
>
>
The following shutdown request for Bldg. 11 on 12/25 is for your
informtion and comment. Would you please let me know if this has your
approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 11 (entire bldg.)
> Date: 12/25/97
> Day: Thursday
> Time: 8:00 AM - 2:00 PM
> System: Air: supply ventilation, cooling and heating
> Duration: 6 hours
> Reason:
> Preventive maintenance on Air Handlers 1, 2, 3 and 5
>
> Effect:
> Minimal loss of supply and return ventilation, cooling and heating.
> Each Air Handler wil be down one at a time while the others remain
> operational.
>
>