RE:Requested Rescheduled Shutdown for Bldgs. 6 (All, 4 - (Partial
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Dec 10 11:44:38 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: schedule@MIT.EDU, duggins@math.mit.edu, juliec@MIT.EDU, mbj@MIT.EDU,
acherron@MIT.EDU, centor@MIT.EDU, cwilkes@MIT.EDU, rroscoe@MIT.EDU,
jsheahan@MIT.EDU, naylor@MIT.EDU, decarli@MIT.EDU, lpaul@MIT.EDU,
cdernay@MIT.EDU, adams@mitlns.mit.edu, elp@MIT.EDU, farideh@MIT.EDU,
shutdowns@MIT.EDU, Cust-Coach <cust-coach@MIT.EDU>,
Andrea Nichols
<andrea@PLANT.MIT.EDU>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'cehart@mit.edu'" <cehart@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
"'ndk@mit.edu'" <ndk@MIT.EDU>, "'rrhonda@mit.edu'" <rrhonda@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Date: Wed, 10 Dec 1997 11:43:07 -0500
It has been requested that the shutdown for Bldgs. 6 (All), 4 (Partial
-Most) and 2 - All 480 Volt Power be rescheduled to 1/8 PM - 1/9 AM.
Would you please let me know if this new date would be acceptable to you
or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: 2 (All), 4 (Most) and 6 (All)
> > Date: 1/8/9
> > Day: Thursday PM - Friday AM
> > Time: 11:00 PM (1/8) - 7:00 AM (1/9)
> > System: 2 (All 480V Power), 4 (most 208 V power and all 480V power
> and
> > 6 (All 208 and 480V power
> > Duration: 8 hours
> > Reason:
> > To install new high voltage switchgear at electrical substations
> >
> > Effect:
> > Loss of Power: access control, bldg. power, elevators, computers,
> > telephones, lighting; Water: chilled water and de-ionized water;
> Air:
> > supply ventilation; supply cooling, supply heating,
> > exhaust-laboratory, exhaust-general, exhaust-toilet air; Steam
> > condensate return and pumps (2nd shift to dump condensate)
> >
> >
>