RE: Bldgs. 6 (All, 4 - (Partial-most) & 2 (All) Shutdown Requestf

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Dec 9 08:41:54 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Robert Norton <rtnorton@MIT.EDU>
Cc: capozzi@math.mit.edu, juliec@MIT.EDU, mbj@MIT.EDU, acherron@MIT.EDU,
        jcentor@MIT.EDU, cwilkers@MIT.EDU, rroscoe@MIT.EDU, cehart@MIT.EDU,
        jsheahan@mit.edy, naylor@MIT.EDU, lpaul@MIT.EDU, cdernay@MIT.EDU,
        adams@mitlns.mit.edu, elp@MIT.EDU, farideh@MIT.EDU, shutdowns@MIT.EDU,
        Cust-Coach <cust-coach@MIT.EDU>, shutdowns <shutdowns@MIT.EDU>,
        schedule@MIT.EDU, duggins@math.mit.edu
Date: Tue, 9 Dec 1997 08:40:36 -0500

Hi Bob Norton,

Thanks for responding about this shutdown. Since the 3rd shift won't be
able to do this work, (no electricity would make it impossible I know)
couldn't you make arrangements with the coach of the second shift to do
it?

Please advise and thanks.
    Andrea

> ----------
> Hi Andrea, 
> 	I'm Bob Norton a Supervisor /Coach with Building Services, We
> just wanted to let you know that from 11pm to 7am we do the cleaning
> of these areas including the classrooms and restrooms in buildings 2 &
> 4. If you do plan on having this shutdown please let all occupants
> know that we will not be able to do any cleaning that night. Thanks  
> 
> 	NIGHT SHIFT COACHES 
> 
> 
> At 4:25 PM -0500 12/8/97, Andrea Nichols wrote: 
> >> To: 	schedule@mit.edu; duggins@math.mit.edu; capozzi@math.m
> it.edu; 
> >> juliec@mit.edu; mbj@mit.edu; acherron@mit.edu; centor@mit.edu; 
> >> cwilkes@mit.edu; rroscoe@mit.edu; cehart@it.edu; jsheahan@mit.edu; 
> >> naylor@mit.edu; rhondar@mit.edu; decarli@mit.edu; lpaul@mit.edu; 
> >> cdernay@mit.edu; adams@mitlns.mit.edu; elp@mit.edu;
> farideh@mit.edu; 
> >> shutdowns@mit.edu; cust-coach@mit.edu 
> >> Cc: 	shutdown@plant.mit.edu 
> >> Subject: 	Bldgs. 6 (All, 4 - (Partial-most) & 2 (All) Shutdown 
> >> Request for 12/18 - 19 
> >>  
> >>  
> >The following shutdown request for Bldgs. 6 (all), 4 (most) and 2
> (all) 
> >on 12/18-19 is for your information and comment. Would you please let
> me 
> >know if this has your approval or not. 
> > 
> >Thanks very much. 
> > 
> >Andrea Nichols 
> >Operations Center 
> >8-7872 
> > 
> >> Status: Normal 
> >> Building: 2 (All), 4 (Most) and 6 (All) 
> >> Date: 12/18/19 
> >> Day: Thursday 
> >> Time: 11:00 PM (12/18) - 7:00 AM (12/19) 
> >> System: 2 (All 480V Power), 4 (most 208 V power and all 480V power
> and 
> >> 6 (All 208 and 480V power 
> >> Duration: 8 hours 
> >> Reason:  
> >> To install new high voltage switchgear at electrical substations 
> >>  
> >> Effect:  
> >> Loss of Power: access control, bldg. power, elevators, computers, 
> >> telephones, lighting; Water: chilled water and de-ionized water;
> Air: 
> >> supply ventilation; supply cooling, supply heating, 
> >> exhaust-laboratory, exhaust-general, exhaust-toilet air; Steam 
> >> condensate return and pumps (2nd shift to dump condensate) 
> >>  
> >>  
> 
> 
> 