[41087] in Hotline Meeting
Re: Bldgs. 6 (All, 4 - (Partial-most) & 2 (All) Shutdown Request
daemon@ATHENA.MIT.EDU (Robert Norton)
Tue Dec 9 07:20:23 1997
Date: Tue, 9 Dec 97 07:20:11 EST
In-Reply-To: <F1638DEE5A5ACF11911300805FD42DD94D7C93@PLANT.MIT.EDU>
To: Andrea Nichols <andrea@PLANT.MIT.EDU>
From: Robert Norton <rtnorton@MIT.EDU>
Cc: schedule@MIT.EDU, duggins@math.mit.edu, capozzi@math.m.it.edu,
juliec@MIT.EDU, mbj@MIT.EDU, acherron@MIT.EDU, centor@MIT.EDU,
cwilkes@MIT.EDU, rroscoe@MIT.EDU, cehart@it.edu, jsheahan@MIT.EDU,
naylor@MIT.EDU, rhondar@MIT.EDU, decarli@MIT.EDU, lpaul@MIT.EDU,
cdernay@MIT.EDU, adams@mitlns.mit.edu, elp@MIT.EDU, farideh@MIT.EDU,
shutdowns@MIT.EDU, cust-coach@MIT.EDU, shutdown@plant.mit.edu
Hi Andrea,
I'm Bob Norton a Supervisor /Coach with Building Services, We just
wanted to let you know that from 11pm to 7am we do the cleaning of
these areas including the <bold>classrooms and restrooms</bold> in
buildings 2 & 4. If you do plan on having this shutdown please let all
occupants know that we will not be able to do any cleaning that night.
Thanks
NIGHT SHIFT COACHES
At 4:25 PM -0500 12/8/97, Andrea Nichols wrote:
>> To: schedule@mit.edu; duggins@math.mit.edu; capozzi@math.m it.edu;
>> juliec@mit.edu; mbj@mit.edu; acherron@mit.edu; centor@mit.edu;
>> cwilkes@mit.edu; rroscoe@mit.edu; cehart@it.edu; jsheahan@mit.edu;
>> naylor@mit.edu; rhondar@mit.edu; decarli@mit.edu; lpaul@mit.edu;
>> cdernay@mit.edu; adams@mitlns.mit.edu; elp@mit.edu;
farideh@mit.edu;
>> shutdowns@mit.edu; cust-coach@mit.edu
>> Cc: shutdown@plant.mit.edu
>> Subject: Bldgs. 6 (All, 4 - (Partial-most) & 2 (All) Shutdown
>> Request for 12/18 - 19
>>
>>
>The following shutdown request for Bldgs. 6 (all), 4 (most) and 2
(all)
>on 12/18-19 is for your information and comment. Would you please let
me
>know if this has your approval or not.
>
>Thanks very much.
>
>Andrea Nichols
>Operations Center
>8-7872
>
>> Status: Normal
>> Building: 2 (All), 4 (Most) and 6 (All)
>> Date: 12/18/19
>> Day: Thursday
>> Time: 11:00 PM (12/18) - 7:00 AM (12/19)
>> System: 2 (All 480V Power), 4 (most 208 V power and all 480V power
and
>> 6 (All 208 and 480V power
>> Duration: 8 hours
>> Reason:
>> To install new high voltage switchgear at electrical substations
>>
>> Effect:
>> Loss of Power: access control, bldg. power, elevators, computers,
>> telephones, lighting; Water: chilled water and de-ionized water;
Air:
>> supply ventilation; supply cooling, supply heating,
>> exhaust-laboratory, exhaust-general, exhaust-toilet air; Steam
>> condensate return and pumps (2nd shift to dump condensate)
>>
>>