Bldgs. 6 (All, 4 - (Partial-most) & 2 (All) Shutdown Request for

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Dec 8 16:27:14 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: schedule@MIT.EDU, duggins@math.mit.edu, capozzi@math.m.it.edu,
        juliec@MIT.EDU, mbj@MIT.EDU, acherron@MIT.EDU, centor@MIT.EDU,
        cwilkes@MIT.EDU, rroscoe@MIT.EDU, cehart@it.edu, jsheahan@MIT.EDU,
        naylor@MIT.EDU, rhondar@MIT.EDU, decarli@MIT.EDU, lpaul@MIT.EDU,
        cdernay@MIT.EDU, adams@mitlns.mit.edu, elp@MIT.EDU, farideh@MIT.EDU,
        shutdowns@MIT.EDU, cust-coach@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Mon, 8 Dec 1997 16:25:53 -0500

> To: 	schedule@mit.edu; duggins@math.mit.edu; capozzi@math.m it.edu;
> juliec@mit.edu; mbj@mit.edu; acherron@mit.edu; centor@mit.edu;
> cwilkes@mit.edu; rroscoe@mit.edu; cehart@it.edu; jsheahan@mit.edu;
> naylor@mit.edu; rhondar@mit.edu; decarli@mit.edu; lpaul@mit.edu;
> cdernay@mit.edu; adams@mitlns.mit.edu; elp@mit.edu; farideh@mit.edu;
> shutdowns@mit.edu; cust-coach@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. 6 (All, 4 - (Partial-most) & 2 (All) Shutdown
> Request for 12/18 - 19
> 
> 
The following shutdown request for Bldgs. 6 (all), 4 (most) and 2 (all)
on 12/18-19 is for your information and comment. Would you please let me
know if this has your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2 (All), 4 (Most) and 6 (All)
> Date: 12/18/19
> Day: Thursday
> Time: 11:00 PM (12/18) - 7:00 AM (12/19)
> System: 2 (All 480V Power), 4 (most 208 V power and all 480V power and
> 6 (All 208 and 480V power
> Duration: 8 hours
> Reason: 
> To install new high voltage switchgear at electrical substations
> 
> Effect: 
> Loss of Power: access control, bldg. power, elevators, computers,
> telephones, lighting; Water: chilled water and de-ionized water; Air:
> supply ventilation; supply cooling, supply heating,
> exhaust-laboratory, exhaust-general, exhaust-toilet air; Steam
> condensate return and pumps (2nd shift to dump condensate)
> 
> 